JSW Steel rises 2% on gas supply worries HSBC raises Tata Steel target to ₹250 British Steel to supply 120,000 mt billet to Nigeria ₹3,200 crore Tata Steel EAF starts in Ludhiana
Adani Power Limited has placed an order for ₹4,000 crore with state-owned engineering company Bharat Heavy Electricals Ltd (BHEL) to establish the 1,600 MW Raigarh Phase-II Thermal Power Plant in Raigarh, Chhattisgarh. In a filing, BHEL announced that it has been awarded a Letter of Award to oversee the construction and commissioning of two 800-MW power projects using supercritical technology at Raigarh Phase II in Chhattisgarh and to supply equipment.
BHEL's operations in Trichy and Haridwar will produce the boiler and turbine generator, respectively. It will take 31 months for Unit-1 and 35 months for Unit-2 to be supplied.
Also Read : Adani Green Energy completes $750M bond redemption, boosts investor confidence IEA predicts sharp drop in India's oil production by 2030